Project At A Glance

Project At A Glance

Design, Supply & Install of New School Extension

Project At A Glance

Project At A Glance

Design, Supply & Install of New School Extension

Project At A Glance

Project At A Glance

Design, Supply & Install of New School Extension

Project At A Glance

Project At A Glance

Design, Supply & Install of New School Extension

Project At A Glance

Project At A Glance

Design, Supply & Install of New School Extension

Project Information 

Primary School’s new block consisting of two classrooms and toilets - manufactured off site in 12 separate pods while groundworks were completed at the Streatham school. 

 

These units, fully-fitted with underfloor heating powered by an air source heat pump, were then craned into position during the half term holidays

 

Problem

Construcion process had to be low key with a nondisruptive manner of working, which minimised the disruption to the school. Construction and install had to be completed during half term holidays. 
 

Solution

 

Constructing the new classroom off site led to an 85 per cent reduction in transport deliveries to the school and site waste was also reduced by up to 90 per cent. Manufacturing off site allowed the school to operate as normal whilst fewer deliveries also meant less disruption, noise and traffic issues.

Summary 
  • Underfloor Heating 
  • Acrylic Render Finish 
  • Brick Slip Finish
  • Time On Site 1.5 Days 
  • Two New Classrooms & Toilets